PROOF 04:12 NIGHT Tue 4 Aug 2026 · lead D. Achebe

Runs · RUN-4471

Ciabatta ×180

RUN-4471 LATE 22m Formula CB-2 · 68% hydration · mixer 3 · night shift

Still makes the 06:30 van.

Packed by 05:25 against a 06:30 loading window — 65 minutes of slack. It stops making it if DECK 4 is not clear by 05:05, or if the bake runs past 24 minutes. Nothing else on the 06:30 van is waiting on this run.

Stages

1 MIX

Done

01:35 → 01:58
23 min

2 BULK

Done

01:58 → 03:13
75 min

3 DIVIDE

Done

03:13 → 03:32
19 min

4 FINAL PROOF

40 min in

planned 18 min
22 over

5 BAKE

DECK 4

04:18 → 04:40
22 min at 246°C

6 COOL

Bench 1

04:40 → 05:10
30 min

7 PACK

Line B

05:10 → 05:25
15 min

8 VAN

06:30

65 min slack

Why it is late

PLANNED BAKE03:50 → 04:12, DECK 4
WHAT HAPPENED DECK 4 was still holding RUN-4463 (whole wheat sandwich, ×144) which ran 12 minutes long on a cold deck after the 02:40 element fault pulled RACK 4 out and the load was redistributed.
CONSEQUENCE The dough has been in final proof 40 minutes against a planned 18. Ciabatta tolerates over-proof better than a batard; expect a flatter crumb and slightly paler crust. D. Achebe logged it at 04:02 and dropped the deck to 246°C from 250°C.
RECOVERYIn at 04:18, no other change. Do not extend the bake to chase colour — that is what breaks the 06:30 van.

Who it is for

The seven accounts on RUN-4471, 180 ciabatta
ACCOUNTDROPS QTYVAN
Pellet & Vine2 sites4806:30
Meridian Hotel13606:30
The Portland Arms12406:30
Harbour Deli12006:30
Larkspur Café11806:30
Salt House Restaurant11806:30
Rook & Rye11606:30
Total8 drops18006:30

Pellet & Vine takes two drops off one van. If this run short-fills, the Quay site takes the cut and gets a top-up on the 08:00 — they have asked for that twice and both times said it was fine.

1

2

3

4

5

6

7

8

Reading the run…

RUN-4471 is not on this bake day

It was on Tue 4 Aug when the plan was released at 19:48 and is not on it now. Runs move when a day is re-cut — check Wed 5 Aug, or the cancelled list for the last 48 hours.